Can existing mechanical QRH be retained while the PLC, control system or load monitoring is upgraded?

2026-08-28

Potentially, yes, subject to the outcome of a retrofit assessment. Many older terminals still have mechanical QRH that remain suitable for service, while PLC, HMI, communication hardware, load indicators and spare parts may be obsolete, discontinued or difficult to maintain. Before an upgrade, GLEN can assess whether the existing mechanical hooks remain suitable and whether the control system can be replaced independently.

Where the mechanical QRH remain serviceable, the upgrade may include a new PLC/HMI, remote release controls, mooring load monitoring, alarms, historical data recording, and communication with the terminal DCS or CMS. GLEN monitoring and control systems can centrally monitor QRH, BAS, EMS and MLMS, supporting equipment status monitoring, alarm management, historical records, remote monitoring and system diagnostics. The systems can also integrate with DCS, SSL, AIS and CCTV.

Before implementation, functional safety, release logic and sensor compatibility should be confirmed.

Can existing mechanical QRH be retained while the PLC, control system or load monitoring is upgraded? 1

prev
What is the difference between manual, assisted, powered and automatic QRH reset?
Can GLEN replace an existing QRH without rebuilding the original foundation?