The jetty, FSRU and LNGC systems should be engineered as one operational interface rather than treated as three separate systems. The project should define who can initiate an emergency action, which permissions or confirmations are required, whether a release sequence is necessary, how mooring loads are displayed, how ESD signals are exchanged, and which equipment status and alarms are available to each operating party.

This coordination reduces the risk of incompatible assumptions among vessel, FSRU and terminal suppliers. Interface responsibilities should be established during FEED or detailed design and then verified through document review, FAT, system-integration testing and SAT.

GLEN remote release control system supports single-hook or group release, real-time hook-status feedback, and interfaces with CMS, PLC and ESD systems. The final release logic should be governed by the approved control philosophy, cause-and-effect matrix and interface documentation.

How should QRH release logic be coordinated in a Jetty–FSRU–LNGC arrangement? 1

prev
When is a Portable Docking Aid System a better choice than a permanent BAS/DAS?
Is ESD the same as Emergency Mooring Release, and should they operate together?
next
Related questions
GET IN TOUCH WITH Us
Customer service
detect